Plan your renovation schedule from key collection to moving in with our interactive timeline builder
Easily adjust milestones and phases with visual timeline
Automatic sequencing based on HDB regulations
Built-in 2-4 week buffer for unexpected delays
Download ICS file for any calendar app
Add recommended buffer for critical tasks
Total Days
Overall Progress
Critical Tasks
Total Tasks
Collect keys and inspect for defects. Must complete within 7 days for HDB DLP warranty.
Wait for HDB to fix reported defects before renovation starts
Submit and await approval for renovation permit
Confirm all tiles, laminates, fixtures selections
Install protection for floors, windows, and common areas
Remove walls and old fixtures. Must complete within 3 consecutive days (HDB rule)
Clear all demolition waste
Build new walls, shower kerbs, cabinet bases
Install water supply and drainage pipes
Run electrical cables and install outlets
Install air conditioning pipes and trunking
Install false ceiling where required
Install tiles or vinyl flooring
Critical milestone - measure after walls and floors are complete
Factory fabrication of custom carpentry
Install all custom carpentry on-site
Measure for quartz/granite after base cabinets installed
Install kitchen and vanity countertops
Apply primer and first coat of paint
Install shower screens, mirrors
Install sinks, taps, toilet bowls
Apply final coat and touch-ups
Install all light fixtures and switches
Professional cleaning to remove construction residue
Walkthrough with contractor, create defect list
Fix any issues found during final inspection
Enter your BTO key collection date or intended renovation start date
Choose between light, standard, or extensive renovation to adjust timeline
Drag and drop phases to customize based on your contractor's schedule
Download as calendar file or PDF for sharing with your contractor