Average BTO renovation: 8-12 weeks

Renovation Timeline Planner

Plan your renovation schedule from key collection to moving in with our interactive timeline builder

Drag & Drop Planning

Easily adjust milestones and phases with visual timeline

Smart Dependencies

Automatic sequencing based on HDB regulations

Buffer Recommendations

Built-in 2-4 week buffer for unexpected delays

Export to Calendar

Download ICS file for any calendar app

Project Configuration
Set up your renovation project details

Add recommended buffer for critical tasks

0

Total Days

0%

Overall Progress

10

Critical Tasks

26

Total Tasks

Pre-Renovation
2-4 weeks
Planning, permits, and preparation

Key Collection & Defect Check

Critical
7 days

Collect keys and inspect for defects. Must complete within 7 days for HDB DLP warranty.

0%

Defect Rectification by HDB

Critical
14 days

Wait for HDB to fix reported defects before renovation starts

Depends on: key-collection
0%

HDB Permit Application

Critical
14 days

Submit and await approval for renovation permit

Depends on: key-collection
0%

Finalize Material Selection

7 days

Confirm all tiles, laminates, fixtures selections

Depends on: key-collection
0%
Demolition & Hacking
1-2 weeks
Structural changes and removal works

Site Protection Setup

1 days

Install protection for floors, windows, and common areas

Depends on: permit-application, defect-rectification
0%

Wall Hacking & Demolition

Noisy Work
Critical
3 days

Remove walls and old fixtures. Must complete within 3 consecutive days (HDB rule)

Depends on: site-protection
0%

Debris Clearance

1 days

Clear all demolition waste

Depends on: hacking-works
0%
Construction & Infrastructure
3-5 weeks
Building, plumbing, and electrical works

Masonry & Wet Works

Critical
10 days

Build new walls, shower kerbs, cabinet bases

Depends on: debris-clearance
0%

Plumbing Piping

7 days

Install water supply and drainage pipes

Depends on: masonry-works
0%

Electrical Wiring

Critical
7 days

Run electrical cables and install outlets

Depends on: masonry-works
0%

Air-Con Trunking

3 days

Install air conditioning pipes and trunking

Depends on: electrical-wiring
0%

False Ceiling Installation

5 days

Install false ceiling where required

Depends on: aircon-trunking, electrical-wiring
0%

Flooring Installation

Critical
7 days

Install tiles or vinyl flooring

Depends on: false-ceiling, plumbing-rough
0%
Carpentry & Fixtures
3-4 weeks
Custom carpentry and built-in furniture

Carpentry Site Measurement

Critical
1 days

Critical milestone - measure after walls and floors are complete

Depends on: flooring
0%

Carpentry Fabrication (Off-site)

14 days

Factory fabrication of custom carpentry

Depends on: carpentry-measurement
0%

Carpentry Installation

Critical
7 days

Install all custom carpentry on-site

Depends on: carpentry-fabrication
0%

Countertop Measurement

1 days

Measure for quartz/granite after base cabinets installed

Depends on: carpentry-installation
0%

Countertop Installation

3 days

Install kitchen and vanity countertops

Depends on: countertop-measurement
0%
Finishing Works
2-3 weeks
Final touches and completion

First Coat Painting

3 days

Apply primer and first coat of paint

Depends on: carpentry-installation
0%

Glass & Mirror Installation

2 days

Install shower screens, mirrors

Depends on: painting-primer
0%

Plumbing Fixtures Installation

2 days

Install sinks, taps, toilet bowls

Depends on: countertop-installation
0%

Final Coat Painting

3 days

Apply final coat and touch-ups

Depends on: glass-works, plumbing-fixtures
0%

Lighting & Switch Installation

2 days

Install all light fixtures and switches

Depends on: painting-final
0%

Chemical Wash & Cleaning

2 days

Professional cleaning to remove construction residue

Depends on: lighting-installation
0%

Final Inspection & Handover

Critical
1 days

Walkthrough with contractor, create defect list

Depends on: chemical-wash
0%

Defect Rectification

7 days

Fix any issues found during final inspection

Depends on: final-inspection
0%
HDB Renovation Rules & Tips

How to Use This Planner

1

Set Your Key Collection Date

Enter your BTO key collection date or intended renovation start date

2

Select Your Renovation Scope

Choose between light, standard, or extensive renovation to adjust timeline

3

Adjust Milestones

Drag and drop phases to customize based on your contractor's schedule

4

Export Your Timeline

Download as calendar file or PDF for sharing with your contractor

Important HDB Regulations

  • • Renovation hours: 9am-6pm (weekdays/Saturday), no work on Sundays
  • • Noisy works: Must stop by 5pm on weekdays, not allowed on weekends
  • • Hacking: Maximum 3 consecutive days only
  • • BTO renovation must complete within 3 months of permit approval