RenoTake
2

The Contract Deep Dive

The Contract Deep Dive

The 12 essential clauses that must be in your contract, plus payment schedules that keep you in control.

The S$50,000 Mistake: Signing a Vague Contract

Your renovation contract isn't just paperwork—it's your only legal protection when things go wrong. Yet 68% of homeowners sign contracts without reading beyond the price. This section will transform you into a contract expert in 30 minutes.

Every clause matters. Every word counts. The difference between 'supply and install kitchen cabinets' and a detailed specification can cost you S$10,000 in disputes.

Essential Clause #1: Scope of Work

Scope of Work SpecificationSaves S$10,000-15,000
Supply and install kitchen cabinets as follows: - Top cabinets: 12 feet run, 2 feet height - Bottom cabinets: 12 feet run, 3 feet height - Material: EDL E1 Grade laminate, Code: MW1209 (White Oak) - Hardware: Blum soft-closing hinges (Model 71B3550) - Internal: 2 adjustable shelves per unit - Installation: Including all cutting, joining, and edge-banding

Why this matters: Material substitution scams cost homeowners S$8,000-S$15,000 on average. Specificity is your protection against inferior materials being passed off as 'equivalent'.

Essential Clause #2: Payment Schedule

The industry's dirty secret: Most contractors push for front-loaded payments because once they have 60% of your money, they have their entire profit margin. The remaining work becomes optional.

Protected Payment ScheduleSaves Protects entire renovation budget
Payment Schedule: 1. Contract Signing: 15% (Secures slot, minimal risk) 2. Completion of Hacking/Masonry: 25% (Work verified) 3. Carpentry Delivered & Installed: 30% (Most expensive items on-site) 4. Painting & Finishing Complete: 20% (Near completion) 5. After Defects Rectified: 10% (Final protection)

Why this matters: Front-loaded payments remove your leverage. Once contractor has majority of money, motivation to complete quality work disappears.

Essential Clause #3: Timeline with Liquidated Damages

Enforceable Timeline ClauseSaves S$100-200/day in alternative accommodation
Project Timeline: - Start Date: 1 March 2025 - Completion Date: 26 April 2025 (8 weeks) - Liquidated Damages: S$100 per calendar day of delay - Damages waived only for: Force majeure, homeowner-caused delays - Contractor must notify of delays within 48 hours with mitigation plan

Why this matters: Without liquidated damages, contractors have zero incentive to finish on time. With it, a 2-week delay costs them S$1,400.

Essential Clause #4: Material Specifications

Every material must be specified exactly. This is where contractors make their hidden profits through substitution.

ItemProper SpecificationWhy It Matters
TilesNiro Granite NPO1203, 60x60cm homogeneous, 90sqm @ S$4.50/sqftPrevents substitution with cheaper alternatives
LaminateEDL E1 Grade, 0.8mm thickness, Code: specific colorE1 grade ensures low formaldehyde emission
PaintNippon Odourless Premium, 3 coats minimumSpecifies quality and application standard
HingesBlum Model 71B3550 soft-closingPrevents generic hardware substitution
ToiletTOTO C704 one-piece, tornado flushExact model prevents downgrades

Essential Clause #5: Variation Order Procedures

Variation Order ControlSaves Prevents S$5,000-20,000 in scope creep
All changes to original scope must be documented in a Variation Order containing: 1. Description of change 2. Cost impact (+/- S$) 3. Timeline impact (+/- days) 4. Both parties' signatures 5. Work cannot commence until VO is signed 6. Verbal agreements are void 7. Homeowner has right to refuse any variation

Why this matters: Verbal changes are where budgets explode. One homeowner paid S$12,000 extra for 'minor adjustments' that were never documented.

The Complete Contract Checklist

Contract Review Checklist0/14 completed

Critical items: 0/10

Detailed scope of work with specifications

CRITICAL

Progressive payment schedule (max 20% upfront)

CRITICAL

Firm start and end dates

CRITICAL

Liquidated damages clause (min S$100/day)

CRITICAL

Defects liability period (minimum 6 months)

CRITICAL

Material brands and models specified

CRITICAL

Variation order procedures

CRITICAL

Main contractor liability for subcontractors

CRITICAL

Insurance requirements stated

Termination conditions clearly defined

CRITICAL

Dispute resolution process

CRITICAL

Ownership of materials upon delivery

Warranty compilation requirements

Site protection responsibilities

Additional Protection Clauses

  • Subcontractor Liability: 'Main Contractor bears full responsibility for all subcontractors' work quality, conduct, and damages'
  • Insurance Requirements: 'Contractor maintains Public Liability (min S$1M), Workmen's Compensation, and All Risk Insurance'
  • Termination Conditions: Clear grounds including work stoppage >7 days, unapproved deviations, failure to rectify defects
  • Dispute Resolution Hierarchy: 1) Direct negotiation (14 days), 2) CASE mediation, 3) Small Claims Tribunal, 4) Civil litigation
  • Material Ownership: 'All materials become homeowner's property upon delivery to site'